OTHER PROJECTS

FEASIBILITY STUDY FOR INSTALLATION OF STREET LIGHTING ALONG NORTH - SOUTH HIGHWAY

Duration : 2 months (early 1997)

Client : Pengurusan Lebuhraya Berhad (PLB)                

Scope : TNEC undertook a feasibility study to determine and identify the technical & commercial requirements for installation of street lighting along the North - South Expressway (NSE).

DEVELOPMENT OF DATA WAREHOUSE FOR TNB TRANSMISSION NETWORK

Duration : Jul 1997 - Nov 1998

Client : Tenaga Nasional Berhad                

Scope : A part of a 12-year program to implement and utilise microprocessor­ based techno logy for local control, protection, recorders, databank, time reference etc. The 1st phase of the project was intended to utilise the substation control system and databank for selected few grid substation as "proof-of-concept" effort.

RELOCATION OF TNB’S 275KV &132KV OVERHEAD TRANSMISSION LINE TOWER & UNDERGROUND CABLE DUE TO UPGRADING ROAD WORKS FROM ALOR GAJAH TO BANDAR MELAKA

Duration : From July 2002

Client : Tenaga Nasional Berhad              

Scope : The scope of work involved design, supply, install, test and commission of TNB's 275kV and 132kV Overhead Transmission Line, Tower and Underground Cable Diversion works due to upgrading road works from Alor Gajah to Bandar Melaka.

PUSAT LATIHAN GABUNGAN, PASUKAN TEMPUR TENTERA DARAT, FASA DI GEMAS, N.SEMBILAN - 11KV ELECTRICAL INFRASTRUCTURE WORKS

Duration : June 2003

Client : THUB & Kementerian Pertahanan Malaysia           

Scope : The scope of work encompasses 11kV Infrastructure Works for a military base in Gemas, Negeri Sembilan under the Ministry of Defense (MINDEF). Works include 11kV cable laying and installation of transformer and ring main unit.

DIGITAL SIMULATOR SYSTEM

Duration : August 2003

Client : Tenaga Nasional Berhad

Scope : The scope of work encompasses the supply of equipment, fabrication, and engineering work to develop a digital simulator system to train substation operators on SCS systems (Substation  Control  System)

RELOCATION OF TRANSFORMER 60 MVA AND 30 MVA INCLUSIVE OF TERMINATION WORKS FROM TRANSMISSION & SWITCHGEAR

Duration : August 2003

Client : TNB Transmission lpoh, Perak           

Scope : Relocation of Transformer 60 MVA and 30 MVA inclusive of termination works from transmission & switchgear.

RELOCATION OG TNB’S 132KV UNDERGROUND CABLE DUE TO UPGRADING ROAD WORKS AT JALAN MUAR – MELAKA – ALOR GAJAH – SIMPANG EMPAT

Duration : Apr 2003 - Aug 2003

Client : Tenaga Nasional Berhad           

Scope : The scope of work includes design, supply, deliver, erect, string, test, commission and dismantling of TNB's;

  • 132kV transmission line in Kg. Ayer Udang

  • 132kV transmission line in Taman Seri Bayu

  • 275/132kV transmission line in Kg. Paya Datuk

Please reload